Here is the 2 Week Outlook for the High Street Improvements Project for anticipated and projected work through Sept. 4.

With school starting this week, please be extra cautious!

Find out what's happening in Hampton-North Hamptonfor free with the latest updates from Patch.

As with any construction project, weather, unexpected delays or field conditions may change this schedule.

Anticipated Work for the week of Aug. 28.

Find out what's happening in Hampton-North Hamptonfor free with the latest updates from Patch.

  • Monday - Friday:
    • Crew 1: Work will include excavation and construction of the main sewer line between Moulton Road and Mill Road.
    • Crew 2: Work will include the drainage installation between 5 Corners and Old Mill Pond Lane.

Projected Work for the week of Sept. 4.

  • Monday: NO WORK LABOR DAY
  • Tuesday - Friday:
    • Crew 1: Work will include excavation and construction of the main sewer line between Moulton Road and Mill Road.
    • Crew 2: Work will include the drainage installation between 5 Corners and Old Mill Pond Lane.

Look for alternating traffic. This means that we are planning to leave one lane open. Traffic will proceed through the one lane in an alternating pattern stopping vehicles from one direction and then the other. Please leave extra time to get to your destination. Be Safe!