State To Shut Down 3 Road Projects In Belleville, Nutley

Projects to be placed on hold include road repairs on Wallace, Carpenter and Clinton Streets and Tappan Avenue in Belleville.

Belleville, NJ - New Jersey’s recent transportation funding issues are about to impact Belleville and Nutley.

The Governor's Office has released a list of transportation projects that will shut down Friday due to a lack of funding after legislators failed to see eye to eye on a gas tax increase to fuel the state's Transportation Trust Fund (TTF).

The temporary shutdown of $3.5 billion worth of projects will impact both Department of Transportation and NJ Transit initiatives. Work on projects funded by the TTF will stop by 11:59 p.m. on Friday for at least seven days, the governor's office said.

Find out what's happening in Belleville-Nutleyfor free with the latest updates from Patch.

The shutdown follows an Executive Order by Gov. Chris Christie, who last week pledged work would be halted if legislators didn't approve a 23-cent gas tax to fund the state's Transportation Trust Fund, which expired Friday.

TOWN PROJECTS AFFECTED

Find out what's happening in Belleville-Nutleyfor free with the latest updates from Patch.

Affected local projects include:

  • Wallace Street and Carpenter Street (Belleville) - $251,540 current contract
  • Clinton Street and Tappan Avenue (Belleville) - $246,885
  • Nutley Big Tree Garage Oil/Water Separator (Nutley) - $1,700,000

ESSEX COUNTY PROJECTS

Note: Some roads/projects are listed for multiple fiscal years

Other projects that will be shut down in Essex County include:

Wallace Street and Carpenter Street (Belleville) - $251,540 current contract

Clinton Street and Tappan Avenue (Belleville) - $246,885

Replacement of Hoover Avenue Bridge over Third River (Bloomfield) – 772,500

Myrtle Street/JFK Drive North and South Intersection (Bloomfield) - $273,754

Newark Light Rail Bloomfield Station ADA Improvements (Bloomfield) - $9,700,000

Bloomfield Station Tunnel Renovation (Bloomfield) - $3,700,000

Taxiway N/H Lighting Phase II (Caldwell) - $42,693

RW 10-28 Crack Repair & Rejunvenation & RW 10-28 Threshold Lighting (Caldwell) - $5,850

Commerce Road (Cedar Grove) – $235,000

“Various Streets” (East Orange) - $412,350

Lehigh Drive, Section 2 (Fairfield) - $226,000

Rt 46, Rt 287 to Rt 23, Pompton Ave, ITS (Fairfield, Parsippany, Troy Hills) - $252,266

“Various Streets” (Glen Ridge) - $232,000

Lyons Avenue Bridge Over Elizabeth River (Irvington) - $435,000

Orange Garage Oil Water Separator (Irvington) - $1,400,000

Park Place (Irvington) - $377,637

“Various Streets” (Irvington) - $357,820

Orange Garage HVAC Unit Replacement (Irvington) - $2,100,000

Rt 10, Chelsea Dr to Kelly Drive (Livingston, West Orange) - $119,968

Maplewood Hilton Garage HVAC Unit Replacement (Maplewood) - $2,500,000

Maplewood Facility Roof Replacement Phase 1 (Maplewood) - $1,600,000

Bus Operations Control Center Upgrade (Maplewood) - $2,500,000

Maplewood Facility Roof Replacement Phase 2 (Maplewood) - $6,000,000

Hilton Garage Underground Storage Tank Replacement (Maplewood) - $1,700,000

Replacement of Cherry Lane Bridge (Millburn) - $1,000,000

Great Hills Road, Section 3 (Millburn) - $207,100

Maintenance Roadway Repair Contract North, Sub-Region N-3, Contract No. N312, U.S. 22 & I-78 Local (Millburn, Union, Springfield, Westfield, Scotch Plains, Mountainside) - $361,044

Gates Avenue, Section 2 (Montclair) - $221,544

“Various Streets” (Newark) – $1,354,440

“Various Streets” (Newark) – $1,341,640

Structural Repairs & Masonry Restoration (Newark) - $2,746,649

McClellan Street Underpass (Newark) - $69,200

Rt 27, Dehart Place to Rt 21 (Newark, Elizabeth) - $316,317

NJDOT Site Remediation (Newark) - $22,567

NJDOT Site Remediation (Newark) - $144,714

Ironbound Garage HVAC Unit Replacement (Newark) - $700,000

Newark Light Rail Backup Power/Signal System (Newark) - $1,400,000

Newark Light Rail Track State of Good Repair Phase I (Newark) - $3,300,000

Newark Light Rail Maintenance of Way Building Construction (Newark) - $2,900,000

Roosevelt Ave Bridge Design (Newark) - $800,000

Hunter Flyover - Planning and Environmental (Newark) - $2,000,000

Newark Light Rail Track State of Good Repair Phase II (Newark) - $10,200,000

Newark Light Rail Branch Brook Park Station Repairs (Newark) - $700,000

Newark Light Rail Norfolk Station Structural Repairs (Newark) - $1,700,000

Newark Light Rail Vehicle HVAC Replacement (Newark) - $2,100,000

Newark Light Rail Vehicle Base Facility Training Center (Newark) - $500,000

Ferry St Freight Elevator Replacement (Newark) - $500,000

Roosevelt Ave Bridge Rehabilitation (Newark) - $5,300,000

Newark Light Rail Norfolk Street ADA Design (Newark) - $600,000

Newark Light Rail Park Avenue Station Design (Newark) - $1,000,000

Newark Light Rail Communication System Upgrade Phase 1 (Newark) - $400,000

Newark Draw Replacement Study (Newark) - $900,000

Mill Road Design (Newark) - $1,500,000

NJTPD Broad Street Newark Rehabilitation (Newark) - $300,000

Newark Penn Sta. Boiler Building Demolition (Newark) - $1,900,000

Newark Headquarters Capital Lease (Newark) - $4,900,000

Nutley Big Tree Garage Oil/Water Separator (Nutley) - $1,700,000

Orange Bus Garage Underground Storage Tank Replacement (Orange) – $1,500,000

Orange Garage Stair Tower Repair (Orange) - $800,000

“Various Streets” (Orange) - $319,330

“Various Streets” (Orange) - $311,444

Monroe Avenue, Section 2 (Roseland) - $232,000

Becker Farm Road, Section 2 (Roseland) - $217,000

Academy Street (South Orange) - $242,000

Claremont Avenue, Section 2 (Verona) - $226,000

Westover Avenue (West Caldwell) - $226,000

Belgrade Terrace and Cherry Street (West Orange) - $226,000

New Oil-Fired Unit Heater Installation (West Orange) - $33,390

Rt 280 Rockfall Mitigation (West Orange) - $191,975

Mississippi Loop Facility Repair (West Orange) - $200,000