Revised Schedule For Road Paving, Milling In East Brunswick
The County informed the township of the revised dates in a letter to Mayor Brad Cohen.
EAST BRUNSWICK, NJ — The Middlesex County Department of Highways will be milling and resurfacing Cranbury Road, Ryders Lane and Main Street beginning later this month.
Roadwork will take place from 7 a.m. to 3:30 p.m. Monday to Friday.
The County informed the township of the revised dates in a letter to Mayor Brad Cohen.
Find out what's happening in East Brunswickfor free with the latest updates from Patch.
Here are the dates:
Cranbury Road - Fern Road to Kingswood Blvd
Find out what's happening in East Brunswickfor free with the latest updates from Patch.
- Milling: March 29 to March 30
- Paving: April 3 to April 4
- Striping: April 5 to April 5
Cranbury Road - Evergreen Blvd to Ryders Lane
- Milling: March 31 to March 31
- Paving: April 5 to April 5
- Striping: April 6 To April 6
Ryders Lane - House 548 to Milltown Road
- Milling: April 3 to April 5
- Paving: April 6 to April 12
- Striping: April 13 to April 13
Main Street - Delta Gas Station to RR Tracks
- Milling: April 6 to April 06
- Paving: April 13 to April 14
- Striping: April 17 to April 17