Major Road Work Will Start In Livingston This Week: What Drivers, Residents Should Know

Drivers should expect temporary traffic changes, lane closures and shifted traffic patterns on a busy roadway in Livingston.

| Updated
The West Northfield Road culvert replacement project is scheduled to begin soon in Livingston, NJ. (Autumn Johnson/Patch)

LIVINGSTON, NJ — A major road construction project is about to kick off in Livingston.

The West Northfield Road culvert replacement project is scheduled to begin this week and continue for several months.

Subscribe

Work will include replacing the existing culvert over Slough Brook, along with roadway reconstruction, new curbs and sidewalks, driveway improvements, and milling/resurfacing of the roadway.

Here's what it will mean for local drivers, Livingston town officials said:

"Motorists should expect temporary traffic changes, lane closures, and shifted traffic patterns in the area of West Northfield Road, particularly near Slough Brook and Arbor Court, as construction progresses. The approved traffic control plan calls for traffic to be shifted around the work area, with one lane of travel maintained in each direction during portions of the project. Drivers should follow all posted signs and directions from traffic control personnel and allow additional time when traveling through the area."

Township officials noted that a full closure of the culvert/bridge area will also be required during portions of the project.

When a closure is in effect, motorists should follow posted detour signs and seek alternate routes. The traffic control plans include a designated detour plan for periods when the roadway is closed.

Live nearby? Here's what residents should be aware of:

"Residents in the immediate area should also be aware of construction activity during the contractor's standard working hours of 7 a.m. to 3:30 p.m. Access to residential driveways within the work area is required to be maintained throughout construction, although residents may experience temporary changes or restrictions as work progresses."

The project is expected to continue through approximately spring 2027. The exact timeline is dependent on weather.

The work is being undertaken by Essex County with funding from a Local Aid Grant from the New Jersey Department of Transportation.

Send local news tips and correction requests to eric.kiefer@patch.com. Learn more about advertising on Patch here. Find out how to post announcements or events to your local Patch site.

More from Livingston
News | 1d
News | 1d
News | 3d
See more on Patch >

Sign up for free local newsletters and alerts for the
Livingston Patch

Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.

©2026 Patch Media. All Rights Reserved

Do Not Sell My Personal Information