Here is the latest update on the Manasquan Public School District Referendum projects:

Here is the latest update on the Manasquan Public School District Referendum projects:
- Overall Referendum Budget of $12,033,754 (includes 25 percent “soft costs”)
- $3,886,754 for improvements to Elementary School
- $8,147,000 for renovations and additions to High School
- Sod placement completed 11/2/18
- Contractor has provided as-built survey; engineer to perform final punchlist inspection
- NRCM recommends credit change order for ($19,133.03) (remaining amount of unsuitable soils allowance)
- HS Renovations and Additions:
- Contract awarded to Kappa Construction Corp for $6,936,500.00
- Project includes 13,097 square foot addition
- Mansard roof framing and decking is complete; shingle installation is underway
- All HVAC equipment has been started; dehumidification coil for addition installed
- Toilet rooms complete