Schools

Manasquan Public School District Referendum Projects Update

Here is the latest update on the Manasquan Public School District Referendum projects:

Here is the latest update on the Manasquan Public School District Referendum projects:

  • Overall Referendum Budget of $12,033,754 (includes 25 percent “soft costs”)
  • $3,886,754 for improvements to Elementary School
  • $8,147,000 for renovations and additions to High School
  • Sod placement completed 11/2/18
  • Contractor has provided as-built survey; engineer to perform final punchlist inspection
  • NRCM recommends credit change order for ($19,133.03) (remaining amount of unsuitable soils allowance)
  • HS Renovations and Additions:
  • Contract awarded to Kappa Construction Corp for $6,936,500.00
  • Project includes 13,097 square foot addition
  • Mansard roof framing and decking is complete; shingle installation is underway
  • All HVAC equipment has been started; dehumidification coil for addition installed
  • Toilet rooms complete