2022 Sanitary Sewer Rehabilitation Project - Week 5

Please be advised that Insituform Technologies, LLC will continue cleaning and televising procedures for the 2022 Sanitary Sewer Rehabilitation Project (Bid #22-07) on Monday, September 26th, 2022. Find below Insituform’s anticipated daily construction schedule for the week of September 26, 2022, to September 30, 2022. Cleaning and televising procedures will be completed between the hours of 7 AM to 5 PM.
Monday (09/26/22)
Find out what's happening in Montclairfor free with the latest updates from Patch.
- Llewellyn Road between South Mountain Avenue and Eagle Rock Way.
Tuesday (09/27/22)
- Llewellyn Road between Eagle Rock Way and Curtis Terrace.
Wednesday (09/28/22)
Find out what's happening in Montclairfor free with the latest updates from Patch.
- Fulton Street between New Street and Elm Street.
- Miller Street.
Thursday (09/29/22)
- Glenridge Avenue between Bay Street and Highland Avenue.
- Baldwin Street
Friday (09/30/22)
- Lexington Avenue between Maple Avenue and Elm Street.
- Maple Avenue between Lincoln Street and Woodland Avenue.
- Irving Street.
Please note that the above-anticipated schedule may change with the extent of work to be completed.