Ocean City Provides Update On North End Project

Check here to see what work will take place in Ocean City's North End Neighborhood Drainage Project next week.

The following work will take place as part of Ocean City's North End Neighborhood Drainage Project for the week of March 4 to 8, 2019:

  • Feriozzi Concrete will restore curb and gutter in the 100 block of West Avenue. They will also restore the concrete around the pump station in the 200 block of Bay Avenue.
  • Lafayette will work on the pump station in the 200 block of Bay Avenue. They will also begin the check valve chamber at Third Street and Bay Avenue.
  • Delta Line Construction will continue installing the electrical from the service poles to the pump stations at all pump station locations.