PRINCETON, NJ — Princeton will test the soil and groundwater for contamination at the site of its planned $45 million public works facility on River Road, after an early assessment flagged 26 areas of possible concern on the property.
The Princeton Council on Nov. 23 approved two contracts with Artheon Inc., an East Brunswick engineering firm. The first, for up to $97,268, covers a site investigation at 298 River Road. The second, for up to $974,508, covers designing the site and preparing it for a construction bid. Both passed on voice votes.
The new Department of Public Works facility would replace DPW operations at 303 John St. and 27 N. Harrison St., freeing those sites for Princeton's fourth round of affordable housing, according to a Nov. 13 memo to the council from Deanna Stockton, the town's deputy administrator and municipal engineer, and JP Ricci, principal engineer.
The total project is estimated to cost $45,445,018, according to a Sept. 28 estimate by Skanska cited in the memo. About $17.4 million of that is for site work alone.
A preliminary assessment by Artheon earlier this year identified 26 "areas of concern" at the River Road site, according to the memo.
The site investigation will focus on the ones inside the area planned for the new facility.
"This really speaks to the environmental potential contamination on the site," Deanna Stockton, Municipal Engineer and Deputy Administrator, said. "It is not technically professional engineering work. It is more of a soil groundwater investigation work."
The spots to be tested include a waste oil tank, an old transformer in a building that had flooded, former fuel tanks, oil drums, an incinerator building and a former sludge-drying area, according to Artheon's proposal. Crews will drill soil borings, install temporary groundwater wells and scan underground with ground-penetrating radar to look for buried tanks and other features.
The memo says more work may be needed if contamination is found, including more sampling or a cleanup.
The larger contract covers the design of the new facility, including environmental permits, grading, utilities, and the plans and specifications needed to put the job out to bid, Stockton said. It's expected to take about 12 months.
It doesn't cover the building's architecture or construction management. The town will hire an architect and a construction management firm separately, which the memo says is expected within the first three months of Artheon's contract.
The concept plan for the site includes a vehicle storage building of about 30,400 square feet, a maintenance garage with a wash bay, an 8,400-square-foot staff building, a 3,000-ton salt shed, about 60 parking spaces, a fueling station and about 10 acres of disturbed land, according to the memo.
The memo notes that the River Road site "has many site constraints including wetlands, riparian zones, lack of services, and topographic rise of 80 feet over site."
Several council members said they want to stay closely involved as the design moves forward.
"What is the process going to be as this design comes along, so the design does not get ahead of this whole governing body, and at some point, the whole contract is spent, and suddenly the governing body says, 'Wait a minute, that's not the design that we're willing to fund,'" Mayor Mark Freda asked.
Stockton said staff could come back to the council at set points in the design, such as 30 percent and 60 percent complete. The site sits next to Stony Brook, she said, so the town is also working with the regional sewerage authority on site planning.
The size of the vehicle storage building is still undecided. Council president Michelle Pirone Lambros asked when the council would see options and cost estimates for different sizes. Stockton said that should come back around the end of the first quarter of 2027.
Councilman David Cohen said the town should hire an architect soon to keep the project on schedule.
"If we're going to go out to bid in a year, if that's the goal, I just want to make sure that that's moving along at pace," Cohen said.
Freda asked for a work session on the project "fairly soon."
"I understand that we really need the engineering work to help get the cost estimates to be more realistic than what they may have been so far to date, but I just want to make sure we don't get people designing stuff that, at the end of the design period, the majority of the governing body is not going to want done," Freda said.
councilman Leighton Newlin asked whether the environmental costs "could astonish us."
Stockton said there are two kinds of environmental risk at the site. The first is the wetlands, open water and riparian zones, where the Delaware and Raritan Canal Commission and the state Department of Environmental Protection will decide what can be built. The second is contamination.
"Are there materials of concern, whether it be in the buildings to be demoed or in the soil on the site that you have to deal with, which could create a cost that's unknown," Stockton said. "Both are potential slowdowns in the process or cost additive, but that's why we first went through the concept phase and the preliminary assessment."
Have a correction or news tip? Email sarah.salvadore@patch.com
Sign up for free local newsletters and alerts for the
Princeton Patch
Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.