The $610,000 project includes historic fence lines, tree removal, and trail work at Princeton Battlefield State Park.

PRINCETON, NJ — The Princeton Historic Preservation Commission is scheduled to receive a courtesy review presentation on the next phase of a landscape rehabilitation project at Princeton Battlefield State Park, according to a memo from Historic Preservation Officer Sara Quinlan.
The project, led by the Princeton Battlefield State Park and the American Battlefield Trust, is being carried out under a National Park Service American Battlefield Protection Program grant awarded in 2021. The site sits within the locally designated Princeton Battlefield and Stony Brook Settlement Historic District and is listed on both the state and national historic registers, in addition to being a National Historic Landmark, according to the memo.
Quinlan wrote that the current phase, under state register review, primarily involves landscape rehabilitation with limited ground disturbance and that staff finds the project largely adheres to the Secretary of the Interior's standards for treating historic properties and guidelines for historic landscapes.
Find out what's happening in Princetonfor free with the latest updates from Patch.
The fall 2026 phase of work includes trail mowing, tree removal and planting, installation of both historic and non-historic fence lines, meadow rehabilitation, new signage and removal of a deteriorated asphalt trail, according to project plans submitted by the American Battlefield Trust. Planning documents show 219 trees are slated for removal, including dead, hazardous and ash trees affected by disease, with 113 replacement trees required under the borough's tree ordinance.
Supporting research submitted with the application traces the historic fence lines back to accounts from the Jan. 3, 1777, Battle of Princeton. Researchers identified three fences of note for the current project — referred to as the Property Line, the Declivity and the Orchard fences — based on 18th-century deeds, a 1784 painting by James Peale depicting the battle, and multiple firsthand accounts from American and British soldiers who described fences on the battlefield.
Find out what's happening in Princetonfor free with the latest updates from Patch.
Total construction costs for the fall 2026 phase are estimated at $610,000, with $335,000 covered by the American Battlefield Trust and the remainder covered through state Department of Environmental Protection funding, according to a construction estimate included in the application materials.
The New Jersey Forest Service determined in June that the project would not trigger a "No Net Loss" forestry requirement, citing federal forestry criteria for what constitutes forest land, according to email correspondence included in the application.
The Historic Preservation Commission's review is a courtesy review, meaning it is advisory rather than a formal approval action.