Gonnelli Wants Secaucus' Newest Data Center Reduced To 2 Stories

Mayor Gonnelli plans to speak at the NJSEA meeting Thursday.

| Updated
CoreSite wants to turn this building next to Shetik soccer fields on County Avenue into a four-story, 500,000-square-foot data center. Gonnelli said he wants it to be reduced to two stories. (Carly Baldwin/Patch)

SECAUCUS, NJ — The New Jersey Sports & Exposition Authority (NJSEA) will hold their monthly meeting at 10 a.m. Thursday, at their headquarters building in DeKorte Park in Lyndhurst.

Not only have several Secaucus residents who are against data centers said they plan to attend the meeting and confront NJSEA leadership, but Secaucus Mayor Mike Gonnelli said he plans to speak at the meeting, as well.

Subscribe

Gonnelli said he plans to tell the NJSEA Board of Commissioners he wants the town's newest proposed data center, at 215 County Avenue, to be reduced to two stories. This is the new CoreSite data center the town already approved to open next to Shetik soccer fields. It is currently planned to be 500,000 square feet and four stories tall. Construction hasn't started yet to turn that existing building into a data center.

Gonnelli said he told the NJSEA he's coming and going to speak.

The NJSEA is the state authority that determined the zoning for 14 towns in the New Jersey Meadowlands, and also created the Meadowlands Master Plan. Data centers are allowed to open throughout much of Secaucus, in areas zoned for light industry. Data center companies say Secaucus is attractive because of all the fiber optic cables and its location right next to New York City.

Former NJSEA CEO (and former speaker of the state Assembly) Vinny Prieto said last week that Gonnelli is not punting (reporter's word) or passing the buck when he blames the NJSEA for establishing the zoning laws in 88 percent of Secaucus.

"They really do control the zoning for that much of town," Prieto said. "That's how it was set up. He's not punting on this issue."

Gonnelli said he asked the mayors of the 13 other towns in the Meadowlands (towns like East Rutherford, Carlstadt, etc.) if they would come on Thursday. It remains to be seen if they will back him up. Gonnelli also used to be a commissioner on the NJSEA, but he said he quit three times.

"I sent them a resignation letter for a third time when their new (CEO Jill Hirsch) was sworn in in January. They still call my name at meetings (in roll call)," said Gonnelli.

Hirsch was appointed by Gov. Mikie Sherrill.

An spokeswoman for Hirsch said the NJSEA does hold zoning jurisdiction over portions of each town in the Meadowlands district. However, she said in 2015 the town of Secaucus elected to become an "opt-out" municipality. It's still unclear what that means.

Also, Secaucus resident Tom Roarty attended last week's Oct. 13 meeting between two data center companies (CoreSite, Equinix), the town, and PSE&G and Veolia water company. He posted this summary of what was said at the meeting on Facebook.

Tom Hindell contributed reporting.

Another view down County Avenue. (Carly Baldwin/Patch)
(Carly Baldwin/Patch)
More from Secaucus
News | 1d
News | 1d
News | 5d
See more on Patch >

Sign up for free local newsletters and alerts for the
Secaucus Patch

Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.

©2026 Patch Media. All Rights Reserved

Do Not Sell My Personal Information