Business & Tech
Plainview Company Helping Rebuild Boardwalk
Project underway to replace hurricane-damaged decking in Long Beach.
A Plainview company is helping to rebuild the Long Beach boardwalk.
The much-anticipated deck construction on the Long Beach boardwalk began Monday and continued on Tuesday morning.
This decking work is a 'preliminary-assessment build out,β Long Beach City officials stated.Β
It is being completedΒ prior to full construction which starts on June 17. Crews and cranes are now fully operational along the 2.2-mile boardwalk.
Grace Industries, the Plainview firm hired to rebuild the beach townβs 2.2-mile boardwalk, is building the tropical hardwood decking across 10 bays, or 180 feet, this week before full construction commences the following week, according to an announcement posted on the cityβs website.
βWhile it may appear at times that work has stalled, rest assured this is being used as a βpreliminary-assessment build outβ prior to full construction which starts on June 17,β reads the announcement. βThe purpose of this preliminary build is to determine how long certain procedures will take.β
The announcement continues: βPlease note that we are still on schedule to have a half-mile portion (five blocks/20% of the boardwalk) completed by the 100-day milestone of July 23.β
Find out what's happening in Plainviewfor free with the latest updates from Patch.
City Manager Jack Schnriman and Jim LaCarrubba, the cityβs commissioner of public works, told Patch as much last week after Tuesdayβs City Council meeting,Β when questions arose about theΒ work performed to dateΒ to rebuild the boardwalk that was heavily damaged in Hurricane Sandy last October.
βIf they fail to meet that milestone there is a $15,000 penalty a day for each day until it is met,β Schnriman said about the penalties the city will deduct from invoices submitted by Grace Industries if the firm fails to meet contractual milestones on the $44.2 million construction project.
Find out what's happening in Plainviewfor free with the latest updates from Patch.
LaCarrubba also talked to CBS News last week about the project that started with a series of public input meetings to discover what features residents would like the new boardwalk to include, with storm-resistance materials ranking as the top priority. βIf we would have just built what was here, yeah it would have been done; it wouldnβt have accomplished anything; it would have been a big waste of taxpayer money.β