Pipe Bursting Begins on Inwood
Work continues on this major construction project

Utilicon Corp. crews completed the first pipe bursting run at Inwood Boulevard Aug. 10.
Since mid-July, the contractor crews have installed over 1,200 feet of polyethylene sewer pipe with the connecting manholes and home laterals at Inwood and Bellaire. Excavation will continue through next week to connect the remaining Bellaire sewer laterals and install the next Inwood sewer section between Durrell and Canterbury.
Find out what's happening in Avon-Avon Lakefor free with the latest updates from Patch.
Residents will be notified 48 hours ahead of schedule where crews will be working and asked to reduce water usage while laterals are being connected. Local access traffic will be maintained and motorists are advised to drive with caution. Concerns relating to water and sewer construction should be directed to Avon Lake Municipal Utilities at 440-933-6226 during workdays or 440-933-3229 on weekends and holidays.
Issues relating to road repairs should be directed to the City Engineering Department at 440-930-6141. Click here for more information or to download the Inwood-Dellwood-Bellaire presentation. Future updates will be available on Twitter and ALMU’s website at www.avonlakewater.org