Cleveland Massillon Road Construction And Closure
Local businesses can be accessed from Route 18 and Cleveland Massillon Road.
August 7, 2020
The road will close on September 14, 2020 for 45 days from Elgin Drive/Rosemont Blvd. north to Bywood Drive for the removal of a pipe for Schocalog Creek and the installation of a box culvert. Local businesses can be accessed from Route 18 and Cleveland Massillon Road.
Find out what's happening in Fairlawn-Bathfor free with the latest updates from Patch.
Storm sewers and waterline installations for the entire project will also be installed at this time from Bywood Drive to the I-77 ramps. Detours will be posted and the driving public is asked to watch out for workers and obey all signage and detours. Expect Delays!
Find out what's happening in Fairlawn-Bathfor free with the latest updates from Patch.
This press release was produced by the City of Fairlawn. The views expressed are the author's own.