Kids & Family
Turnpike Construction Updates for April 9-14
Many roads near the turnpike in Whitpain Township will see daytime construction during the week.

The Pennsylvania Turnpike Commission has released its weekly construction update for work on the "NE Extension Reconstruction and Widening Project" from the Mid-County Interchange to Berks Road.
According to the release, general impacts to the following areas include excavating, fence installation, clearing, stump grinding, crushing rock and hauling. Neighborhoods adjacent to the areas may experience "minimal noise impacts," the release says.
Whitpain Township
Union Meeting Road, Jolly Road
Find out what's happening in Lower Gwynedd-Ambler-Whitpainfor free with the latest updates from Patch.
Installing drainage Monday, April 9, through Wednesday, April 11, from 7 a.m. to 6:30 p.m.
Find out what's happening in Lower Gwynedd-Ambler-Whitpainfor free with the latest updates from Patch.
Wentz Road, Horseshoe Drive, Lucy Drive, Michaels Lane, DeKalb Pike, Cherry Road
Excavating mainline and installing permanent soil nail wall Monday, April 9 through Saturday April 14 from 7 a.m. to 6:30 p.m.
Jolly Road, Meadow Drive, Mermaid Lake
Excavating for retaining walls Monday April 9 through Saturday, April 14 from 7 a.m. to 6:30 p.m.
Jolly Road, Meadow Drive, Wick Lane, DeKalb Pike
Installing sound barrier posts, excavating mainline and installing permanent soil nail wall Monday April 9 through Saturday, April 14 from 7 a.m. to 6:30 p.m.
Sheffield Drive, Larchwood Drive, Old Arch Road
Installing sound barrier posts and T-wall panels Monday, April 9 through Friday, April 13 form 7 a.m. to 6:30 p.m.
Oak Ridge Drive, Rosewood Drive, East Side Drive
Excavating for mainline retaining walls and placing embankment Monday, April 9 through Friday, April 13 form 7 a.m. to 6:30 p.m.
Jolly Road Mainline Bridge
Monday, April 9, through Saturday April 14 from 7 a.m. to 6:30 p.m.
Wentz Road Mainline Bridge
Monday, April 9, through Saturday April 14 from 7 a.m. to 6:30 p.m.
Township Line Road Mainline Bridge
Monday, April 9, through Friday April 13 from 7 a.m. to 6:30 p.m.
North Wales Road and Skippack Pike Mainline Bridges
Monday, April 9, through Saturday April 14 from 7 a.m. to 6:30 p.m.
Plymouth Township
Walton Road, Apollo Road, Township Line Road
Excavating for mainline, retaining walls, detention basins/sediment traps and placing embankment Monday, April 9 through Saturday, April 14 with shifts 24 hours a day.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.