U.S. 1 Lanes In Bensalem Closed Next Week

Drivers are advised to allow extra time when traveling through the work area because backups and delays will occur.

BENSALEM, PA — Drivers on U.S. 1 next week will encounter right-lane closures heading both northbound and southbound between Old Lincoln Highway and Rockhill Drive.

The lane closures are scheduled Monday, Nov. 26, through Friday, Nov. 30, from 8 p.m.-6 a.m. Crews will be doing paving work as part of a project to rebuild, widen and improve a 1.3-mile stretch of the highway in Bensalem.

Drivers are advised to allow extra time when traveling through the work area because backups and delays will occur. All scheduled work depends on weather, transportation officials said.

Find out what's happening in Bensalemfor free with the latest updates from Patch.

This corridor improvement project is the first of three construction contracts to rebuild and widen U.S. 1, replace aging bridges and install safety enhancements along a four-mile section of the expressway from just north of Philadelphia to just north of Route 413 (Pine Street) in Middletown Township and Langhorne Borough. Improvements under this first contract include:

  • Constructing a third travel lane along U.S. 1 in each direction from the Route 132 (Street Road) interchange to just north of the Pennsylvania Turnpike Interchange;
  • Building an auxiliary lane along U.S 1 in each direction between the Route 132 (Street Road) and Pennsylvania Turnpike interchanges;
  • Raising the profile of U.S. 1 from south of the Route 132 (Street Road) Interchange to north of the Pennsylvania Turnpike Interchange to improve vertical clearances for U.S. 1 structures over Route 132 (Street Road), the Pennsylvania Turnpike, and the Pennsylvania Turnpike Interchange ramps;
  • Upgrading U.S. 1 interchanges at Route 132 (Street Road) and the Pennsylvania Turnpike;
  • Adding a northbound right-turn lane along U.S. 1 from Old Lincoln Highway to Route 132 (Street Road);
  • Reconfiguring the Route 132 (Street Road) Interchange and adding a ramp from Route 132 (Street Road) eastbound to U.S. 1 southbound;
  • Increasing the existing loop ramp radius to improve design speed to 30 miles-per-hour and incorporating a second lane on the U.S 1 northbound exit ramp to the Pennsylvania Turnpike;
  • Removing the existing bridge that carries U.S. 1 over a closed private access road; and
  • Reconstructing four bridges.

Allan A. Myers, Inc. of Worcester, Montgomery County is the general contractor on the project, which has a total price tag of $97,352,764. It's being financed with 80 percent federal funds and 20 percent from the state.

Find out what's happening in Bensalemfor free with the latest updates from Patch.

All work on the project is expected to be completed by the end of 2022, Wolf's office said.