FALLS TOWNSHIP, PA — Falls Township Supervisors have signed off on a final land development deal for a composting facility.
At a recent meeting, supervisors approved the amended final land development plan for McGill Fairless Hills Composting Facility at 600 Tyburn Road.
The company will construct a 37,560-square-foot addition to its existing 124,650-square-foot composting facility, which is situated on a 15.59-acre parcel.
Other improvements include construction of Biofilter 3, installation of an acid scrubber system and construction of two buildings to enclose the two existing biofilters with an exhaust stack.
The acid scrubber system will be installed within an existing building, and a tank building, roofed tank containment area, and roofed tanker bay will be installed to support the acid scrubber.