Construction activities will continue on Langhorne-Yardley Road and Woodbourne Road throughout May, PennDOT said.
MIDDLETOWN TOWNSHIP, PA — Construction activities will continue on Langhorne-Yardley Road and Woodbourne Road throughout May, PennDOT said.
The Pennsylvania Department of Transportation said that various construction activities are scheduled through May on the road under a $10.9 million project to improve traffic congestion and safety on Langhorne-Yardley Road at the Bridgetown Pike and Woodbourne Road intersections in Middletown Township.
Drivers are advised that a periodic weekday lane closure with flagging will be in place through Friday, May 29, from 9 a.m. to 3 p.m. at the following locations:
Find out what's happening in Levittownfor free with the latest updates from Patch.
- Langhorne-Yardley Road between Bridgetown Pike and Briggs Road.
- Woodbourne Road between Kilburn Road and the entrance to Core Creek Park.
Drivers are advised to allow extra time when travelling through the work areas because backups and delays will occur.
Find out what's happening in Levittownfor free with the latest updates from Patch.
All scheduled activities are weather-dependent.
Under this contract, PennDOT’s contractor constructed a new single-lane roundabout at Langhorne-Yardley Road and Bridgetown Pike.
The roundabout was reopened on Aug. 15, 2025.
Work also included realigning the roadway; installing upgraded traffic signals, stormwater management, ADA curb ramps, signage, and lighting; performing resurfacing operations; and improving mobility for pedestrians and bicyclists.
Improvements on Langhorne-Yardley Road and its intersection with Woodbourne Road include realigning the northern leg of Woodbourne Road and constructing auxiliary turn lanes on all four approaches.
The eastern leg of Woodbourne Road will also be widened to allow for a left turn lane on Langhorne-Yardley Road approaching Erica Drive.
James D. Morrissey, Inc. of Philadelphia, is the general contractor on this project, which is financed with 80 percent federal funds and 20 percent state funds.
For more information, including pedestrian and bicyclist improvements, visit the Langhorne-Yardley Road Intersection Improvement Project page.