Road Paving Project Begins In Bristol Township

Bristol Township officials said the road paving project will last for several days this week.

BRISTOL TOWNSHIP, PA —The township's annual road paving project is set to begin on Tuesday.

Bristol Township's 2024 Road Paving Schedule is expected to last all week, weather permitting, township officials said.

Here is the schedule:

Find out what's happening in Levittownfor free with the latest updates from Patch.

  • Tuesday, May 28 —Milling of Old Orchard Lane from Bath Road to Harrison Street and milling of all of Hatfield Street.
  • Wednesday, May 29 —Milling of Ford Road from Bath Road to Interstate 95 bridge, milling of all of Grasspond Road and all of Gun Road.
  • Wednesday, May 29 —Paving of Old Orchard Lane, paving of Hatfield Street, and paving of Ford Road.
  • Thursday, May 30 —Milling of Wistar Road from the bridge to the Middletown Township line and paving of Grasspond Road.
  • Friday, May 31 —Paving of Gun Road and paving of Wistar Road.

Anyone with questions or who needs additional information should contact Charlie Dearnley, Public Works Director, at 267-716-3152. Dearnley may also be contacted at the start of the resurfacing project by any resident who needs assistance or special accommodation due to health or medical issues while the contractor is working on their road.

"We would like to thank you in advance for your patience and understanding during the upcoming construction," township officials said. "Your cooperation is greatly appreciated."