PPL got permission from Lower Macungie Township commissioners to close one section of Mill Creek Road Aug. 6 and another Aug. 7.

Lower Macungie Township commissioners gave PPL permission to close two sections of Mill Creek Road over Aug. 6 and 7 to rebuild a transmission line.
-- On Aug. 6, Mill Creek will be closed from Route 100 to Pioneer Drive.
-- On Aug. 7, Mill Creek will be closed from Pioneer Drive to Penn Ave.
Find out what's happening in Lower Macungiefor free with the latest updates from Patch.
Kyle Swartzentruber of PPL told township commissioners that the closings were necessary to rebuild a transmission line that transmit power to Mack Truck's plant as well as Victaulic Co. The closings will run from 7 a.m-3 p.m. both days and traffic will be detoured.