REFUSE/RECYCLE/YARD WASTE SCHEDULE:
- Monday – District 1 Refuse
- Tuesday – District 2 Refuse
- Wednesday - Yard Waste
- Thursday - District 1 Recycling
- Friday – District 2 Recycling
- Yard Waste: Note that the Yard Waste collection is back to the normal schedule.
UTILITIES:
Find out what's happening in Radnorfor free with the latest updates from Patch.
- Miller Brothers continues PECO gas main work in the South Devon area & Beaupre sections of the Township.
- Along with the above work South Devon Ave. will be closed a block at a time for gas main installation.
- Darby Paoli Road will be closed beginning Monday, August 31 for PENNDOT bridge work
- County Line Road closure between Matsonford Rd. & North Spring Mill (320)*PECO will be performing tree trimming.*County Line will be closed weekdays 8 a.m. to 4 p.m. & Saturdays 9 a.m. to 4 p.m.*Residents will have access to their homes.*PECO continues to replace 42 Telephone poles on County Line Road in the area of Wistar Road.
- Roberts Road will be closed between Robinhood and Woodlea Roads from May 4 to August 7 for culvert work.
- PENNDOT night-time paving work continues.
- PECO Paving Restoration taking place Monday, September 22 & Tuesday, September 23 on Runnymede between Bloomingdale and South Wayne and Lansdowne between Audubon and Runnymede. There will be road closures, Homeowners will have access.
- Aqua will be installing 2,104 feet of Water Main and water services on Radnor Street Road starting at Eagle and working down to Walnut. They will proceed on Walnut to Woodland Ave. Work is scheduled to begin the week of the August 24, no later than August 31. Work hours are 7 a.m. to 4 p.m. Residents will have access.
Radnor Township Department of Engineering
- Meet with the Manager and Ward Commissioner to review the West Wayne Preserve and Darby Creek Flood Reduction study.
- Meet with the Manager and Ward Commissioner to present the 90% plan set for the Morris Road Street Project.
- Continue to meet with residents affected by Hurricane Isaias.
- Review revised plans for Poplar – North Wayne Pedestrian Safety Project.
- Review Plans for North Wayne Sidewalk Project.
- Review revised plans for the King of Prussia/Eagle Road Intersection Improvement project.
- Respond to builders and developers’ inquiries.
- Perform Site Inspections.
- Review land development application plans.
- Continuing weekly meetings with consultants (Carroll, Gilmore, Gannett Fleming) on all infrastructure projects.
- Process grading permit, clearing, sidewalk, and U&O applications.
- Respond to and meet with residents on various concerns.