Radnor's Superpave Program Begins Monday, See The Schedule Here

Radnor Township's annual road paving program will begin next week. It is expected to last until July 21. See details here.

RADNOR TOWNSHIP, PA — Numerous roads in Radnor Township will be paved under the township's annual Superpave Program.

The 2025 Superpave Program will begin Monday and is expected to be completed by June 21.

Parking will be prohibited on streets that are being paved under the program.

Find out what's happening in Radnorfor free with the latest updates from Patch.

Drivers should allow extra travel time when paving is underway, as delays may occur.

Below is the 2025 Superpave Program schedule:

Find out what's happening in Radnorfor free with the latest updates from Patch.

Wistar Road

  • Milling — July 7 and July 8
  • Paving — July 10

Weldon Lane

  • Milling — July 7 and July 8
  • Paving — July 10 and July 11

Hardwicke Lane

  • Milling — July 7 and July 8
  • Paving — July 10 and July 11

Brookside Circle

  • Milling — July 8 and July 9
  • Paving — July 14

Harbison Road

  • Milling — July 8 and July 9
  • Paving — July 14

Chamount Drive

  • Milling — July 9 and July 10
  • Paving — July 14

Knox Road

  • Milling — July 9 and July 10
  • Paving — July 14 and July 15

Watch Hill Road

  • Milling — July 10 and July 12
  • Paving — July 15

Hothorpe Road

  • Milling — July 10 and July 12
  • Paving — July 15

Abrahams Lane

  • Milling — July 11 and July 14
  • Paving — July 15 and July 16

Woodcrest Circle

  • Milling — July 14 and July 15
  • Paving — July 16

Woodcrest Road

  • Milling — July 14 and July 15
  • Paving — July 16

East Beechtree Lane

  • Milling — July 15 and July 16
  • Paving — July 18

Francis Avenue

  • Milling — July 15 and July 16
  • Paving — July 18

Midway Road

  • Milling — July 16 and July 17
  • Paving — July 18 and July 21

Valley Forge Terrace

  • Milling — July 16 and July 17
  • Paving — July 18 and July 21

See the Superpave map online here.

Contact Ben Wagner, PE, at bwagner@radnor.com or 610-688-5600 with questions about the program.