Tilghman Street Bridge Projects on Schedule

The Tilghman Street bridge over Chapmans Road and the one over the Norfolk Southern Railroad are expected to be done at the end of August.

The Tilghman Street bridge construction projects in are on track to be completed at the end of August, according to PennDOT.

Ron Young, spokesman for the Pennsylvania Department of Transportation District 5, said the project to replace the deck and beams on the Tilghman Street Bridge over the Norfolk Southern Railroad and the complete replacement of the bridge over Chapmans Road are moving along on schedule. 

“They’ve been working long days, sun up to sundown and weekends,” Young said.

Find out what's happening in Upper Macungiefor free with the latest updates from Patch.

The construction began in mid-March and is projected to cost $4.9 million. Originally, it had been estimated to take 1 ½ years but the contractor is condensing the work into a shorter time frame by working longer hours, Young said.  

For a while some truckers were ignoring the signs that directed them to take the official posted detour route that took them on Route 22, Interstate 78 and 100. But started cracking down on trucks that were traveling the side roads detour a few weeks ago and that seemed to discourage them, Young said.

Find out what's happening in Upper Macungiefor free with the latest updates from Patch.

“I haven’t gotten any complaints in weeks,” he said.

Early in the construction, some of the near the construction complained that the detours were confusing some of their customers.

“When it first went into effect there was some growing pains,” Young said. “We still get a few people who aren’t familiar with the area who make a wrong turn here and there.”