This post was contributed by a community member. The views expressed here are the author's own.

Neighbor News

Falmouth Wind Turbine Litigation Exceeds One Million

Falmouth Massachusetts spending up to $300,000.00 every 6 months wind turbine litigation. Ten ongoing legal cases continue no end in sight.

Falmouth Wind Turbine Number One Land Court Today 

Falmouth Massachusetts ground zero for poorly placed wind turbines in USA. The turbines have taken health-property rights in 21 communities

Falmouth, Massachusetts USA June 24, 2016

Falmouth Wind Turbine Number One Land Court Today
Wind turbine plaintiffs attorney today in Massachusetts land court , 6/24/2016, filed a revised motion to intervene and a motion to transfer their other zoning case involving the same parties in superior court .

Expert disclosures are due by September 30, 2016.
Expert disclosures will comply at a minimum with requirements for expert interrogatories.
Parties have leave to take expert depositions.
The discovery period closes on October 31, 2016.
The case number is: 16 MISC 000234

Falmouth Massachusetts is spending up to $300,000.00 every 6 months on wind turbine litigation.

The Town of Falmouth has been in court since 2011

The town currently has over ten ongoing legal cases over the wind turbines

Falmouth Wind I is shut down 24/7
Falmouth Wind II is shut down 12/6 and all day Sundays

The health and financial fiasco continues ...............