A start date for work to install an 8-inch sewer main inside Bluebonnet Circle, as well as on South University Drive and West Biddison S ...

November 09, 2021

A start date for work to install an 8-inch sewer main inside Bluebonnet Circle, as well as on South University Drive and West Biddison Street, is now known: Thursday, Nov. 11.

Find out what's happening in Dallasfor free with the latest updates from Patch.

Construction will start at University Drive and the north side of Bluebonnet Circle. The contractor will leave door hangers on businesses and residences to inform everyone that construction is starting.

The contractor is Gra-Tex, and residents may also see construction crews from Circle H, a subcontractor to Gra-Tex.

Find out what's happening in Dallasfor free with the latest updates from Patch.

An existing, deteriorated 8-inch sewer main that is just east of Bluebonnet Circle, between Park Ridge Boulevard and West Biddison Street, will be abandoned. This line is behind businesses that front Bluebonnet Circle.

The project is in an area bound by the alley behind Circle C Cleaners and Mellow Mushroom to the north, Mission Street to the east, Bluebonnet Circle to the south and Rogers Avenue to the west. The project is in City Council District 9 and impacts the Bluebonnet Hills Neighborhood Association.

This project is part of the TCU Area Lead Replacement and Infrastructure Improvement project. View the project page on the city website. 

To learn more, contact Project Manager Suby Varughese via email or at 817-392-7803.

 

 