Frisco Weekly Roadwork Roundup - May 3, 2021
These projects will be completed within two weeks (weather permitting) unless otherwise noted.

May 2, 2021
(May 2, 2021) The following roadway projects may impact traffic this coming week. These projects will be completed within two weeks (weather permitting) unless otherwise noted.
Find out what's happening in McKinney-Friscofor free with the latest updates from Patch.
Pavement Repairs
- Kimber Ln, Sheli Ln & Lesli Ln (Preston North Neighborhood) (PDF) - Contractor will be milling off the top 1.5 inches of asphalt and then City crews will be putting down a new asphalt overlay.
- Westbound College Pkwy at Hillcrest Rd (PDF)
- Del Webb Blvd between Tailwater Trl and Flatcatcher Dr (PDF)
- 6851 Kettle Wood Dr between Springwood Dr and Ridge Creek Pkwy (Hunters Creek Neighborhood) (PDF)
Ongoing Pavement Repairs
Find out what's happening in McKinney-Friscofor free with the latest updates from Patch.
- 12021 Southbound Dallas Pkwy between Longwood Dr and Eldorado Pkwy (PDF)
- Castle Dr at Kings Ridge Rd (Preston Gables Neighborhood) (PDF)
- 11209 Jereme Trail between Sunrise Ln and Lexington Pl (Plantation Resort Neighborhood) (PDF)
- 6309 Pitchfork Ranch Dr between Flat Top Ranch Rd and Cedar Ranch Rd (Phillips Creek Ranch Neighborhood) (PDF)
- 11105 Ormond Ln between Belle Chasse Ln and Ashland Belle Ln (Plantation Resort Neighborhood) (PDF)
- 9720 Williford Trail (Preston Manor Neighborhood) (PDF)
- 4448 Limerick Lane (Heritage Green Neighborhood) (PDF)
- Alley between Castle Dr and Camelot Dr (Kings Ridge Addition Neighborhood) (PDF)
Ongoing Pavement Reconstruction Project