Round Rock Weekly Roadwork Roundup β October 5, 2020
There are eight roadway projects that may impact traffic this coming week.
October 4, 2020
(October 4, 2020) There are eight roadway projects that may impact traffic this coming week. All of the projects listed below will be completed within two weeks (weather permitting) unless otherwise noted.
Find out what's happening in Round Rockfor free with the latest updates from Patch.
Pavement Repairsβ Southbound Parkwood Blvd at Stonebrook Pkwy (PDF)β 10804 Promise Land Dr (PDF) (Plantation Resort Neighborhood)
Pavement Patch Repairsβ Westbound Main St near Carroll Cir (PDF) - work is estimated to take one day with the lane closure between 9 a.m. and 3 p.m.β Westbound Lebanon Rd near 4th Army Dr (PDF) - work is estimated to take one day with the lane closure between 9 a.m. and 3 p.m.β Southbound Legacy Dr, north of Cotton Gin Rd (PDF) - work is estimated to take one day with the lane closure between 9 a.m. and 3 p.m.
Find out what's happening in Round Rockfor free with the latest updates from Patch.
Ongoing Alley Repairsβ 8100 Pacific St (PDF) (Preston Oaks Neighborhood)Ongoing Pavement Repairsβ Northbound Teel Pkwy near Morgan Hill Rd Intersection (PDF)β 11317 Jereme Trail (PDF) (Plantation Resort Neighborhood)