Traffic Alert: Falmouth Lane Shifts Begin Monday Night

Work will also include paving Friday night, June 5, according to the Virginia Department of Transportation.

A change in traffic pattern means we’re one step closer to finishing the road project at the Falmouth intersection at Route 1 and Route 218.

The Virginia Department of Transportation announced the following shifts beginning Monday night, June 8.

  • Route 1 southbound: Both existing lanes will be shifted to the right, through the intersection, onto the newly constructed southbound lanes. The existing turning and through traffic movements will remain in place from the new lanes.
  • Route 218 westbound: Both existing lanes will be shifted slightly to the right onto the new pavement.
  • Route 218 eastbound: The existing single lane will be shifted slightly to the right onto the new pavement.

VDOT also announced paving plans this weekend that will impact some traffic:

Find out what's happening in Fredericksburgfor free with the latest updates from Patch.

Motorists traveling west on Route 218 (Butler Road) near Route 1 will be restricted to one lane on Friday. Crews will be paving the new westbound lanes on Butler Road from 9 a.m. to 3 p.m.

When finished, the intersection will haveΒ new turn lanes and through lanes. The project is expected to be complete in September.