Doolittle Construction Company is doing the first phase of work on Shoreline's 2011 Bituminous Surface Treatment (BST) project

On Thursday, the Doolittle Construction Company began the first phase of work on Shoreline’s 2011 Bituminous Surface Treatment (BST) project in the Echo Lake neighborhood. The first phase will take approximately four days to complete.
The second phase will occur several days later and take a day or two to complete. The entire project is to be completed by August 20.
Paving work is weather dependent and in order to take advantage of a window of good weather, crews will be working this Saturday, Aug. 13 from 8 a.m. to 7 p.m. Work will occur between 5th Ave N.E. and Meridian Ave. N. and N. 185th and N. 205th Streets. On Sunday, August 14, there will be street sweeping to pick up the excess rock on the streets that were paved on Saturday.
Find out what's happening in Shoreline-Lake Forest Parkfor free with the latest updates from Patch.
First Avenue NE will not be included in the work on Saturday. Work there will occur next week.
If you have any questions or concerns about the paving work, call Tom Doolittle of the Doolittle Construction Company at (425) 455-1150. To learn more about BST in Shoreline, visit shorelinewa.gov/index.aspx?page=787.