A hydraulic lift will be added to the loading dock over winter break to accommodate the vehicles that will make deliveries to the school.

October 29, 2020

Ruby Bridges Elementary continues to await for the school’s certificate of occupancy, while also working through the project’s punch list.

Find out what's happening in Woodinvillefor free with the latest updates from Patch.

A hydraulic lift will be added to the school’s loading dock over winter break to accommodate the vehicles that typically make deliveries to the school. Additionally, the necessary seismic bracing adjustment that is isolated to the school’s mezzanine area on the third floor will also be completed during the break. All other areas of the school have been approved by Snohomish County to be occupied by students and staff, when it is safe to return to buildings as defined by the District’s staged approach. The project remains on budget.

This project was made possible by the generous support of Northshore voters, who approved the 2018 bond.

Find out what's happening in Woodinvillefor free with the latest updates from Patch.

Continue to follow the school’s progress by visiting our construction page.


This press release was produced by the Northshore School District. The views expressed here are the author’s own.