Village Of Sussex : Road Program Update: August 3, 2021
See the latest announcement from the Village of Sussex.
08/04/2021 12:16 PM
The 2021 Road Program project consists of repairs and replacements of mostly concrete pavements in the Village, along with repairs to the Village’s sanitary, storm and water systems along these roadways. The project also includes construction of sidewalk along Silver Spring Drive.
Find out what's happening in Sussexfor free with the latest updates from Patch.
Work has been underway since March 29, 2021, and is scheduled to continue through the end of October 2021; however, the contractor is on track to be done with all of the work by Labor Day. Below is a brief summary of the work to be done along each road segment and the contractor’s current anticipated schedule for that segment. Please watch these E-Blasts and the Village’s website for schedule adjustments and refinements as work progresses. On the website, you will also find traffic disruption information for each segment of the project and a Project Boundary Map.
Sussex Road and Village Drive
This portion of the project is essentially complete.
Industrial Park Ditch Grading and Pond Construction
This work is scheduled to begin the week of August 10 (approximately 3-4 weeks to complete).
Miller Way
This portion of the project is done.
Hi-Tech Drive
Asphalt pavement repairs and replacements are complete. The contractor needs to do a little grading to improve drainage at the south end of the road and also needs to complete lawn restoration in the coming weeks.
Silver Spring Drive
The remainder of the sidewalk is scheduled to be poured Friday, August 6. The contractor will be doing some adjustments to the retaining this week which needs to be done before the sidewalk is poured in that area. Lawn restoration will follow.
Find out what's happening in Sussexfor free with the latest updates from Patch.
Asphalt driveway tie ins on the south side of Silver Spring Drive and the pavement patch at Hickory are scheduled for August 13. Asphalt driveway tie ins on the north side of Silver Spring Drive are tentatively scheduled for August 20. For those of you who live on Silver Spring Drive, please continue to place your garbage and recycling carts in the parking lane about 2 feet from the curb until the barrels are removed so that the trucks can reach them on garbage day.
Good Hope Road (Waukesha Avenue intersection to the railroad tracks) and Waukesha Avenue (Keystone Drive to Good Hope Road intersection)
These portions of the project are essentially complete. Minor clean up and restoration work still needs to be done. The small asphalt pavement patch on Field Drive north of Good Hope Road is scheduled for August 13.
This press release was produced by the Village of Sussex. The views expressed here are the author’s own.