The 2021 Road Program project consists of repairs and replacements of mostly concrete pavements in the Village, along with repairs to the Village’s sanitary, storm and water systems along these roadways. The project also includes construction of sidewalk along Silver Spring Drive.

Work has been underway since March 29, 2021, and is scheduled to continue through the end of October 2021; however, the contractor is on track to be done with all of the work by Labor Day. Below is a brief summary of the work to be done along each road segment and the contractor’s current anticipated schedule for that segment. Please watch these eBlasts and the Village’s website for schedule adjustments and refinements as work progresses. On the website, you will also find traffic disruption information for each segment of the project and a Project Boundary Map.

Find out what's happening in Sussexfor free with the latest updates from Patch.

Sussex Road and Village Drive
Two way traffic has been restored. Portions of two asphalt driveways along Sussex Road and a small asphalt patch replacement at Village Drive and Main Street still need to be completed. Lawn restoration is nearly complete. Thanks to all of the businesses for your patience while we completed this much needed project.
Industrial Park Ditch Grading and Pond Construction
This work will begin in early August (approximately 3-4 weeks to complete).
Miller Way
This portion of the project is done.
Hi-Tech Drive
Asphalt pavement repairs and replacements are scheduled to take place the week of July 26. The pavement will be removed on Tuesday and Wednesday, July 27 and 28, underground work is scheduled for Thursday, July 29, and the paving is scheduled for Friday, July 30. The rain date for paving will be either Saturday, July 31 or Monday, August 2.
Silver Spring Drive
The retaining wall should be done this week. The rest of the sidewalk and driveways will be completed by next week. Lawn restoration will follow. For those of you who live on Silver Spring Drive, please continue to place your garbage and recycling carts in the parking lane about 2 feet from the curb until the barrels are removed so that the trucks can reach them on garbage day.
Good Hope Road (Waukesha Avenue intersection to the railroad tracks)
The pavement repairs are complete. Final clean up, joint sealing and lawn restoration will be done in the next couple of weeks. The landscaping crew intends to get back to lawn restoration after completing the retaining wall along Silver Spring Drive.
Waukesha Avenue (Keystone Drive to Good Hope Road intersection)
Waukesha Avenue pavement repairs are complete. Lawn restoration will be done in the next couple of weeks with the Good Hope Road restoration.