This will be the final E-Blast for the 2021 Road Program.  The majority of the work is done or nearly done on the project.  The contractor will be back in the coming weeks to take care of punch list items that have been identified by Village staff.  This does require pavement replacements in some areas but traffic impacts will be minor with only lane closures while the work is being done and the concrete cures.

The 2021 Road Program project consisted of repairs and replacements of mostly concrete pavements in the Village, along with repairs to the Village’s sanitary, storm and water systems along these roadways.  The project also included construction of sidewalk along Silver Spring Drive.

Find out what's happening in Sussexfor free with the latest updates from Patch.

Sussex Road and Village Drive

This portion of the project is essentially complete.

Industrial Park Ditch Grading and Pond Construction

This pond has been graded.  Topsoil is expected be installed next week and then the pond will be seeded.  The ditch work has started and is expected to be completed next week.

Miller Way

This portion of the project is done.

Hi-Tech Drive

Asphalt pavement repairs and replacements are complete.  The contractor needs to do a little grading to improve drainage at the south end of the road and also needs to complete lawn restoration in the coming weeks.

Silver Spring Drive

Topsoil work is underway and seeding is scheduled in the coming days.  Once that work is done, the barrels will be removed.

For those of you who live on Silver Spring Drive, please continue to place your garbage and recycling carts in the parking lane about 2 feet from the curb until the barrels are removed so that the trucks can reach them on garbage day.

Good Hope Road (Waukesha Avenue intersection to the railroad tracks) and Waukesha Avenue (Keystone Drive to Good Hope Road intersection)

These portions of the project are essentially complete.  Final restoration work still needs to be done. 