Politics & Government
Summit Ave. Construction Project Delayed Until June
Construction updates are also available for Northview Road, Main Street, Greenmeadow Drive, Dunbar Ave., W. Moreland Blvd. and the bypass.

WAUKESHA, WI — Citing a round of wet and unseasonable weather earlier this year, Waukesha officials said the contractor hired to do the job has pushed the start date of the Summit Ave. project back to early-to-mid June.
The City of Waukesha will be reconstructing Summit Avenue and replacing/upgrading underground utilities from Greenmeadow Dr. to N. Grandview Blvd. Also, as part of this project, the asphalt pavement along Summit Avenue will be resurfaced from N. University Dr. to Greenmeadow Dr.
The scope of work for this project along Summit Avenue will include water main up-sizing, large diameter storm sewer installation, and pavement reconstruction and resurfacing. The sanitary sewer throughout the project limits will also be rehabilitated via lining, and most sanitary sewer laterals will be replaced.
Find out what's happening in Waukeshafor free with the latest updates from Patch.
More Project Updates:
- Northview Road (Meadowbrook to Tallgrass Cir.)
- Main Street (Lombardi Way to Manhattan Drive)
- Greenmeadow Sewer Project(intersection of Greemeadow Dr. /Michigan Ave. to intersection of College Ave/Sentry Dr.)
- W. Moreland Blvd (Riverview Ave to Delafield St.)
- West Waukesha Bypass - DOT project
Find out what's happening in Waukeshafor free with the latest updates from Patch.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.