Canwood Street Improvement Construction Schedule for Next Two Weeks


The following information from the City of Agoura Hills website is the construction schedule and traffic information for the Canwood Street Improvements.

Construction Schedule: June 17-June 28

Week of June 17th - No work is scheduled on Monday, Tuesday and Wednesday. Grinding is scheduled for Thursday and Friday. Pavement will be rough through the weekend. Traffic Control Phases 3, 4 and 5 will be in place. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.

Week of June 24th - Cold-In Place Recycling of pavement is scheduled for this week from Alfonso to Strawberry Hill. Traffic Control will be in place. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.

Find out what's happening in Agoura Hillsfor free with the latest updates from Patch.

TRAFFIC CONTROL

Please be aware that the following traffic controls will be expected for the Canwood Street Improvements project (Please see photo).

Phase 1a/1b is expected to be in place from the first week of May until early June. Eastbound traffic will be closed from Forest Cove to Strawberry Hill and a detour will be in place.

Find out what's happening in Agoura Hillsfor free with the latest updates from Patch.

Phase 2a/2b is expected to be in place during the 1st week of June. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.

Phase 3, 4 and 5 is expected to be in place from Mid-June to Early July. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.