Prep Work Begins On Beaumont's $3.5M 'Mid-Year Street Program'
The work will cover approximately 36 lane miles of downtown Beaumont roadway.
January 4, 2021
Prep work has officially begun on the City's Mid-Year Street Improvement Project
Find out what's happening in Banning-Beaumontfor free with the latest updates from Patch.
The project will consist of slurry seal, asphalt overlay, and asphalt rubber aggregate membrane (ARAM) treatment to approximately 36 lane miles. Construction will be divided into five areas located throughout the downtown area of Beaumont.
The $3.5 million project is a result of an amendment to the Fiscal Year 2021-2025 Capital Improvement Plan (CIP) and reallocation of funding following a fiscal year-end review of finances. The project will utilize unrestricted General Fund Reserve dollars and reimbursement through a grant from CalRecycle for the use of ARAM.
Find out what's happening in Banning-Beaumontfor free with the latest updates from Patch.
The Mid-Year Street Enhancement Project follows the recent completion of $3 million of street improvements including the reconstruction of Beaumont Avenue and the enhancement of several downtown streets.
This press release was produced by the City of Beaumont. The views expressed here are the authorās own.