City Of Hermosa Beach: Construction Notice | CIP 669 Park Restrooms Project Begins 9/20

See the latest announcement from the City of Hermosa Beach.

09/09/2021 5:35 PM

 

Find out what's happening in Hermosa Beachfor free with the latest updates from Patch.

Construction is beginning on CIP 669 City Park Restrooms and Renovations Project on Monday, September 20. This project will improve restroom access at four parks around the City (Fort Lots-Of-Fun, Seaview Parkette, South Park, and Clark Field).

Find out what's happening in Hermosa Beachfor free with the latest updates from Patch.

Construction Schedule:

Construction begins September 20, 2020 and is expected to last between six and eight months. Work hours will be Monday - Friday, 8 a.m. - 6 p.m.

What to Expect:

  • Restrooms at Clark Field and South Park will be closing. ADA-compliant portable toilets and handwash stations with hand sanitizer will be available nearby and serviced thrice-weekly.
  • Noise (especially during demolition)
  • Minimal dust and smells
  • All four parks will stay open, but work areas will be fenced off.
  • There will be downtime at construction sites since we are using the same general contractor for all four parks. 

Ciros Ganji 

Cell: 951.893.3398 

View construction notice

Learn more about the project 


This press release was produced by the City of Hermosa Beach. The views expressed here are the author’s own.