A Big Sandbox at Crown Valley and Alicia Parkways
The parking lot areas are among the construction sites at City Hall this week.
There's a lot of dirt being spread around at the new City Hall this week. That's because the parking lot areas are being mapped out. Some might say it looks like a big sandbox.
Here are construction activities anticipated for the week of May 16-20, according to Dan Fox, community development director.
- Continue site work with curb and gutter in the parking lot areas.
- Begin installation of irrigation on slopes.
- Remove and replace sidewalks along Alicia and Crown Valley parkways.
- Continue interior painting and finish work.
- Continue work on fountain at front entry area.
The new City Hall is expected to be completed by late August. Workers broke ground in October.