Politics & Government
City Hall Looking Like a Real Building
Construction continues with final plastering and installation of the air-conditioning unit.
The new Laguna Niguel City Hall is looking more and more like a real building. The final plaster is being applied, and other tasks are being done. This week the following is the anticipated construction activity for the week of March 21 to 25.
- Install roof-mounted air-conditioning unit.
- Begin installation of site parking area screen walls and trash and generator enclosures.
- Continue exterior plaster final color coat and painting of building.
- Continue installation of roof tiles.
- Continue interior drywall.
- Continue installation of windows.
- Continue installation of stone veneer on building and planter walls.
The new City Hall is scheduled to be completed by the end of August.