The following is the anticipated construction activity for the week of Feb. 7-11 at the new Laguna Niguel City Hall.
- Continue installation of window systems.
- Continue wrapping building in paper and wire lath.
- Continue installation of pre-cast trim at the arcade arches.
- Continue metal stud framing of interior soffits in the council chambers and community room.
- Continue work on roof and eaves.
The new Laguna Niguel City Hall is expected to open in August.