The following is the anticipated construction activity for the week of March 14-18 at the corner of Alicia and Crown Valley parkways.
It's full steam ahead at the new , where painting and tiling are in full force. Here's what's being worked on this week:
- Continue interior drywall.
- Continue installation of accent tiles in entry arches and bell tower.
- Begin installation of windows.
- Begin installation of stone veneer on building and planter walls.
- Continue installation of roof tiles.
The new City Hall is expected to open in late August.