Politics & Government
Parking Lot and Flooring Under Way at City Hall
Here's the construction work scheduled for the week of May 9-13 at the corner of Alicia and Crown Valley parkways.
Lots of work is going on this week at the new , especially inside. According to Community Development Director Dan Fox, this week's construction work should include:
- Pouring raised planters and seat wall at front entry and in .
- Beginning underground electrical in parking lot area.
- Beginning cleaning and preparing for finish flooring in office areas.
- Beginning wall coverings in lobby area.
- Continuing work on at front entry area.
Look for the new City Hall to be completed by the end of August.