The following construction activities are anticipated for the week of June
13-17, according to Dan Fox, community development director.
- Continue placement of pedestrian hardscape features and entry monument sign.
- Continue work on the fountain in the entry plaza.
- Complete hardscape work in amphitheater courtyard area.
- Complete tile flooring in entry lobby.
- Continue interior cabinets and finish work.
- Complete installation of irrigation and trees on interior slopes.