2021 Road Rehabilitation Project – UPDATED SCHEDULE AS OF NOVEMBER 10

This schedule is subject to change based on weather and construction delays.

November 12, 2021

As the Paradise Drive Sidewalk Widening Project nears completion, the Town has begun moving forward with the next phase of our Capital Improvement Program in this area.

Find out what's happening in Larkspur-Corte Maderafor free with the latest updates from Patch.

Our contractor, Ghilotti Brothers, Inc, started construction for the 2021 Road Rehabilitation Project on September 7th, 2021.

This project involves the installation of ADA curb ramps, improving drainage and making repairs to the storm system, installing new signage, refreshing striping, and other related roadwork. The 2021 Road Rehabilitation Project involves the complete resurfacing of Paradise Drive from San Clemente Drive to Seawolf Passage in both directions.

Find out what's happening in Larkspur-Corte Maderafor free with the latest updates from Patch.

Additionally, the following streets within the Marina Village, Mariner Cove and Madera Del Presidio neighborhoods will be resurfaced following the work performed by the 2020 Sewer Rehabilitation Project:

Initial work involving identified tree removal, concrete work, drainage repair and the establishment of the ADA ramps will begin upon the start of construction.

Paving and resurfacing segments are scheduled later in the project following infrastructure work expected to continue through end of November (weather permitting).

Prior to the resurfacing of specified streets, effected residents will be notified in advance of the disruption of access by door hangers, no parking barricades, and electronic message boards on effected streets.

Construction began on September 7th, 2021. Schedule Updated 11/10/2021 as follows:

This schedule is subject to change based on weather and construction delays. The contractor will notify homeowners when work will begin on their street. For more information on the 2021 Road Rehabilitation Project, visit the Town’s project page by clicking here. If you have further questions regarding this work, please contact Senior Civil Engineer Chris Good at (415) 927-5794 or cgood@tcmmail.org.

View the project page and updated schedule