Crews Removing 4th 504-Foot Section Of Old Bay Bridge Today, Thursday
The work can be viewed live on the internet.

BAY AREA, CA -- Caltrans is removing the fourth of five 504-foot sections of the old eastern span of the Bay Bridge today and Thursday, Caltrans officials said.
Work lowering the 504-foot truss started at about 6:30 a.m. and will take two days with crews working 12 to 14 hours per day. The section will be lowered onto barges and hauled away.
Constructed in 1935, the bridge was decommissioned in 2013 when a new self-anchored suspension span was finished to replace it. Crews have slowly been deconstructing the obsolete span since then and demolition is
scheduled to continue until 2018.
Find out what's happening in Martinezfor free with the latest updates from Patch.
One reason for the long process is because of extensive measures taken to mitigate impact on the surrounding environment, according to Caltrans. As the truss is lowered to barges in the bay, work crews are being
advised by a bird deterrence contractor to make sure there is little impact on wildlife.
"Although we have already successfully completed this truss lowering operation on three recent occasions, we are diligent in our continued commitment to safety and the environment," chief bridge engineer Brian Maroney said in a statement.
Find out what's happening in Martinezfor free with the latest updates from Patch.
If weather conditions are favorable with no high winds, work on the truss could be finished by the end of today.
The work is being broadcast live on the internet at
https://www.youtube.com/channe... and
https://www.youtube.com/channel/UCky7z7aBl7uEwHDLhMtsgsw/live.
--Bay City News/Image via Bay Bridge Demo on YouTube