Community Corner
Are the Rods on Bay Bridge's New Eastern Span Safe?
Tests say "YES," according to transportation officials.

By Bay City News Service:
Metropolitan Transportation Commission chairman Steve Heminger said Tuesday that he is pleased that final tests confirm that most of the steel rods on the new eastern span of the Bay Bridge are safe and donβt need to be replaced.
But Heminger expressed concern that a 2011 investigation that found problems with some of the rods, which secure earthquake shock absorbers to the deck of the eastern span, wasnβt brought to his attention or made public until recently.
Find out what's happening in Millbraefor free with the latest updates from Patch.
In March 2013, about one-third of the initial batch of 96 bolts that were installed in 2008 failed when they were tightened.
However, Caltrans figured out a temporary solution that allowed the new eastern span to open on schedule on Labor Day in 2013 and crews completed a permanent fix in December.
Find out what's happening in Millbraefor free with the latest updates from Patch.
[RELATED: San Francisco-Oakland Bay Bridge Top 10 Finalist for Americaβs Transportation Award]
Referring to the 2011 investigation that identified problems with some of the rods, Heminger said, βThis strikes me as a pretty big fish that got awayβ because it might have been possible to fix the problem quicker and less expensively if more people had been told about it right away.
Speaking at a meeting Tuesday of the MTCβs Toll Bridge Program Oversight Committee, which oversees Bay Bridge construction, Heminger also said itβs βtroublingβ that the information wasnβt made available to the committee last year when it was looking into problems with the rods.
A final report on the rod issue that was released at the committeeβs meeting Tuesday said that extensive tests of about 2,600 bolts on the new eastern span indicate that they are safe.
Brian Maroney, Caltransβ chief engineer, said, βThis report is great news because we donβt have to remove hundreds of rods.β
But Heminger and Caltrans officials spent part of the meeting addressing another issue that recently emerged with the new eastern span. Engineers recently discovered that about three dozen of the 424 steel anchor rods at the base of the spanβs tower had been sitting in potentially corrosive water although they were supposed to be kept dry.
Bill Casey, Caltranβs construction manager for the new eastern span, said the rodsβ exposure to water could be a potential concern if there was long-term corrosion that was not addressed. He said the agency is addressing the issue by testing all of the anchor rods and using dehumidifiers to dry the rods that were exposed to water.
John Fisher, a structural engineer who is a member of the Toll Bridge Programβs seismic peer review panel, said he believes the leaks are mostly caused by rainwater, as opposed to bay water that may have gotten into the rods, so the problem should be easily fixable.
βIn my opinion, this is not a major issue, itβs an issue of maintenance,β Fisher said.
Maroney said he also thinks the problem is manageable, saying, βI donβt see it being a stress corrosion cracking issue.β
Asked if drivers should feel concerned about driving on the new span, Maroney said, βAbsolutely not. This is a safe bridge.β