35 Mill Valley Roads to Get Fresh Pavement: Is Your Street On the List?

The repaving will take place Aug. 1 through Aug. 10. Here's a list of streets and closure dates.

Mill Valley, CA — More than $4 million in municipal tax service revenues will spent this year by the city of Mill Valley to improve roads and sewer facilities.

The first phase of the city's annual road pavement project is already under way, City Manager Jim McCann said Thursday in a newsletter, with a goal of improving 35 streets throughout Mill Valley.

A significant phase of pavement rehabilitation is scheduled to occur on weekdays between 8 a.m. and 5 p.m., Aug. 1 through Aug. 10. Work crews will use slurry seal — a mixture of water, asphalt emulsion, crushed rock, and additives — to cover the existing asphalt pavement surface of selected streets, according to McCann.

Find out what's happening in Mill Valleyfor free with the latest updates from Patch.

Residents are advised that during the project, the city will need to close the selected roads to vehicle traffic, pedestrians and bicyclists, and restrict parking in certain areas, until work is completed at 5 p.m. each day.

City officials say they recognize that, in addition to this pavement project, there are other ongoing projects, most notably on Miller Avenue and Camino Alto. To minimize impacts to traffic from the infrastructure repair projects, the city said it scheduled much of the road work to take place in the summer, when school is not in session.

Find out what's happening in Mill Valleyfor free with the latest updates from Patch.

"Still, we recognize that this creates an inconvenience and we thank you for your understanding and patience as we improve Mill Valley’s roadways," city officials said.

Here is a list of streets included in this phase, plus closure dates:

  • Mon. Aug 1 Ralston Ave from Summit Ave to Manzanita Place
  • Mon. Aug 1 West Blithedale from King Street to Lee Street
  • Tues. Aug 2 Cushing Drive from Eldridge Ave to Charles Dean
  • Tues. Aug 2 King Street from Corte Madera Ave to Eldridge Ave
  • Tues. Aug 2 Marguerite Ave from Elaine Ave to Summit Ave
  • Tues. Aug 2 Elaine Ave from Marguerite Ave to End
  • Tues. Aug 2 West Blithedale from Lee Street to Ralston Ave
  • Tues. Aug 2 Euterpe Street from Thalia Ave to Carmelita Ave
  • Tues. Aug 2 Dell Lane from East Blithedale to Mountain View
  • Wed. Aug 3 Magee Ave from Tamalpais Ave to Corte Madera Ave
  • Wed. Aug 3 Ethel Ave from Throckmorton Ave to Mirabel Ave
  • Wed. Aug 3 Marion Ave from Hazel Ave to Monte Vista Ave
  • Wed. Aug 3 Heuters Lane from Molino Ave to End
  • Thurs. Aug 4 Elinor Ave from Oakdale Ave to Hillcrest Road
  • Thurs. Aug 4 Ethel Ave from Mirabel Ave to Montford Ave
  • Thurs. Aug 4 Marion Ave from Hazel Ave to Edgewood Ave
  • Thurs. Aug 4 Hazel Ave from Marion Ave to 110 Hazel Ave
  • Thurs. Aug 4 Circle Ave from Hillcrest Road to End
  • Fri. Aug 5 Middle Court from Underhill Road to End
  • Fri. Aug 5 Midhill Drive from Upperhill Road to End
  • Fri. Aug 5 Eldridge Ave from Lee Street to Cushing Drive
  • Fri. Aug 5 Hillcrest Road from Elinor Ave to Circle Ave
  • Fri. Aug 5 Elinor Ave from Hillcrest Road to End
  • Fri. Aug 5 Lee Street from West Blithedale to Eldridge Ave
  • Mon. Aug 8 Aster Court from Azalea Drive to End
  • Mon. Aug 8 Leyton Court from Ashford Ave to End
  • Mon. Aug 8 Somerset Land from Ashford Ave to Lomita Drive
  • Mon. Aug 8 Meadow Drive from Ashford Ave to City Limit
  • Mon. Aug 8 Escalon Drive from Overhill Road to End
  • Mon. Aug 8 Roque Moraes Dr from Kipling Drive to East Blithedale
  • Tues. Aug 9 Dorset Lane from Meadow Drive to East Blithedale
  • Tues. Aug 9 Laurina Road from Overhill Road to End
  • Tues. Aug 9 Overhill Road from Camino Alto to Escalon Drive
  • Tues. Aug 9 Lois Court from Vasco Court to End
  • Tues. Aug 9 Millay Place from Roque Moraes Dr to Kipling Drive
  • Tues. Aug 9 Hollyhock Court from Azalea Drive to End
  • Tues. Aug 9 Roque Moraes Dr from Kipling Drive to End
  • Tues. Aug 9 Jacklyn Terrace from Seaver Drive to End
  • Tues. Aug 9 Roque Moraes Ct from Roque Moraes Dr to End
  • Wed. Aug 10 West Blithedale from King Street to Hillside Ave
  • Wed. Aug 10 Mountain View from Carmelita Ave to East Blithedale
  • Wed. Aug 10 Marguerite Ave from West Blithedale to Elaine Ave
  • Wed. Aug 10 Hill Street from East Blithedale to Oakdale Ave
  • Wed. Aug 10 Madrona Street from Throckmorton Ave to Lovell Ave

The city will have a construction manager available to help with traffic control and address questions or concerns from residents during the time the slurry seal is being applied. Anyone with specific questions related to the work being done on their street may contact city of Mill Valley Construction Manager Jeffrey Palin at jeff.palin@weareharris.com or 925-765-9134.

To read more about this roadway improvement project, visit the city's website.