This post was contributed by a community member. The views expressed here are the author's own.

Community Corner

City Offices: First Floor Concrete Begins

The past two weeks have seen a lot of activity on the city offices site.

The mechanical, electrical, plumbing (MEP) and fire protection subcontractors installed deck rough-in for each of their systems in anticipation of the first floor concrete deck pour (see video attached to the article).

The MEP subcontractors also started installing their systems in the basement, including hangers and supports for the fire sprinkler system, light and mechanical equipment layout, and installation of conduit for power and communications.

Find out what's happening in Novatofor free with the latest updates from Patch.

Once the first floor concrete is complete, scaffolding will soon be erected around the perimeter of the building, to begin installation of metal framing for the perimeter walls.

Download the movie

Find out what's happening in Novatofor free with the latest updates from Patch.

The views expressed in this post are the author's own. Want to post on Patch?