The contractor is currently working both on the bridge deck and underneath.
August 10, 2020
Crews will be paving the former median area in preparation for one lane of westbound traffic to be diverted onto the eastbound bridge in mid-August.
Find out what's happening in Rancho Santa Margaritafor free with the latest updates from Patch.
The contractor is currently working both on the bridge deck and underneath. Paving over the former median area is complete and will allow one lane of westbound traffic to be diverted onto the eastbound bridge. The projected timeframe for the traffic shift is Tuesday, August 18th.
Please note that all landscaping, including replacement of Magnolia trees, will occur upon completion of the bridge maintenance project.
Find out what's happening in Rancho Santa Margaritafor free with the latest updates from Patch.
Thank you for your patience as we conduct infrastructure improvements for the community, and please drive safely.
This press release was produced by the City of Rancho Santa Margarita. The views expressed here are the authorβs own.