Construction, Installation and Maintenance: June 27 to July 4, 2014
Construction, Installation and Maintenance: June 27 to July 4, 2014
June 27, 2014
Construction
There are no major construction projects at this time.
Find out what's happening in San Brunofor free with the latest updates from Patch.
Installation
Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) Project
The CBOSS PTC Project is an advanced signal system that will equip the corridor and the trains with federally-mandated safety technology and will increase system capacity to help accommodate future ridership demand.
Find out what's happening in San Brunofor free with the latest updates from Patch.
The project will monitor and, if necessary, control train movement in the event of human error. This will increase safety by:
- Eliminating the risk of train-to-train collisions.
- Reducing risk of potential derailments by enforcing speed limits.
- Providing additional safety for railroad workers on the tracks.
- Improving grade crossing performance to reduce gate downtime and improve local traffic circulation.
The CBOSS PTC Project is also a key component of the Caltrain Modernization Program, which will electrify the Caltrain Corridor by 2019. An electrified Caltrain will be cleaner, quieter, and will upgrade the system to provide faster and/or more frequent service to more stations and more riders.
To implement the project, at various locations, Caltrain will be identifying utilities, digging a small trench and/or boring close to the tracks to install a fiber optic cable. In order to maintain daytime train service, Caltrain will be performing some of this work at night.
Redwood City
Day work will occur June 30–July 3 from 7 a.m. to 5 p.m. to identify utility lines, pull inner-duct through existing conduit in the ground, and pull/test fiber optic cable. Crews will also install conduit on the Dumbarton Spur. Crews will work as quietly as possible.
Night work will occur June 29-July 3 from 8 p.m. to 6 a.m. Crews will be boring and/ or digging a small trench to install conduit for a fiber optic cable. Neighbors may experience some minor installation noise during this time and lights will be used in the area to help provide visibility. Crews will work as quietly as possible.
Menlo Park
Day work will occur June 30–July 3 from 7 a.m. to 5 p.m. to identify utility lines, pull inner-duct through existing conduit in the ground, and pull/test fiber optic cable. Crews will also install conduit on the Dumbarton Spur. Crews will work as quietly as possible.
Night work will occur June 29-July 3 from 8 p.m. to 6 a.m. Crews will be boring and/ or digging a small trench to install conduit for a fiber optic cable. Neighbors may experience some minor installation noise during this time and lights will be used in the area to help provide visibility. Crews will work as quietly as possible.
Unincorporated San Mateo County, Atherton, Palo Alto, Mountain View, Sunnyvale, Santa Clara, San Jose
Day work will occur June 30–July 3 from 7 a.m. to 5 p.m. to identify utility lines, pull inner-duct through existing conduit in the ground, and pull/test fiber optic cable. Crews will work as quietly as possible.
Night work will occur June 29-July 3 from 8 p.m. to 6 a.m. Crews will be boring and/ or digging a small trench to install conduit for a fiber optic cable. Neighbors may experience some minor installation noise during this time and lights will be used in the area to help provide visibility. Crews will work as quietly as possible.
For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.caltrain.com/CBOSSPTC or email caltrainptc@samtrans.com.
Maintenance
Caltrain will perform routine maintenance at several locations next week. To avoid disruptions to service, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.
San Francisco
Sunday, June 29, to Thursday, July 3, crews will replace ties at the 4th and King streets station. Sunday, June 29, to Thursday, July 3, crews will resurface rail between the 22nd Street and Bayshore stations.
San Francisco to San Jose
Saturday, June 28, to Friday, July 4, crews will pressure wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.
San Jose
Sunday, June 29, to Thursday, July 3, crews will weld and grind rail at the Diridon station.
###