The unanimous vote advances design and community engagement, with the first phase expected to finish in spring or summer 2028.

San Rafael's new library and community center at Albert Park will move into design under a contract approved by the City Council. The council voted 5-0 on Monday, Nov. 2, to approve the agreement with XL Construction Corporation.

The facility is funded by a citizen initiative voters passed in November 2024. This is the city's first use of progressive design-build for a major capital project.

“We are responding to what our community has said that they wanted,” said Mayor Kate Colin, “having a building that reflects our community vision and values and that will be here for the next generation is amazing.”

Find out what's happening in San Rafaelfor free with the latest updates from Patch.

The contract covers Phase 1, including conceptual and schematic design, community engagement, initial entitlements and permitting, and design development. That work will establish a guaranteed maximum price for final design and construction, allowing the team to address risks before locking in the price.

XL Construction and design partner SOM were selected through a competitive process that drew eight qualified teams, with three finalists interviewed. “I am absolutely confident in this team that we have assembled and that the collaboration that we are putting in place will bring forward an exceptional facility for our community,” said Councilmember Maribeth Bushey.

Find out what's happening in San Rafaelfor free with the latest updates from Patch.

The council also authorized a construction labor agreement negotiated with the North Bay Building & Construction Trades Council and the North Coast States Regional Council of Carpenters. The agreement satisfies a state requirement for a skilled and trained workforce on local progressive design-build projects.

Phase 1 is expected to finish in spring or summer 2028. Staff will then return to the council with a maximum-price amendment for Phase 2, aligned with authorization of construction bond financing.